Project Summary

To lift a production line piece of equipment into a first-floor factory.

Project Brief

A client approached us asking to lift a 2.5 ton packaging unit, in to a first floor factory. The client was advised to go through the roof by others, however we proposed an alternate solution. We gave them a cost saving solution, by lifting it through the side of the building.

The client much preferred our solution, as this was more cost effective, saved on partial deconstruction of the roof and did not require any down time for the factory.

By going via the side of the building, we simply had a single panel removed, and although this made it a very tight fit for the packaging unit to go in via, it meant that by the end of the day, the panel could be reinstalled on to the side of the building.

The Result

By the end of the job, the packaging unit was in place, ready to be used, the side of the building was completely intact, like nothing had happened and we completed another job well done.